LCM Head Quarters Solar System
The Task
LCM set out to reduce electricity costs at its Burnley headquarters while strengthening its environmental performance. A significant proportion of site energy demand came from seven electric vehicle chargers used daily by the team.
To offset this demand and reduce reliance on grid electricity, LCM committed to installing a full rooftop solar energy system.
Scope of Works:
The project was delivered entirely in-house by LCM’s qualified electrical team.
Responsibility covered equipment specification, procurement and full installation. The system design was tailored to meet the energy demands of the headquarters building and on-site EV charging infrastructure.
A total of 120 Jinko Tiger Neo 440W N-Type All Black Mono solar panels were installed across the roof, connected to a Solax X3-Mega G2 40kW three-phase inverter.
Structural mounting, electrical connections and system configuration were completed in line with current regulations and manufacturer requirements.
Installation was carried out over approximately ten weeks. Works were carefully scheduled around client commitments to avoid disruption to day-to-day operations. This phased approach allowed the business to continue operating as normal throughout the project.
Outcomes
The solar system is now fully operational and delivering measurable reductions in grid electricity consumption and energy costs.
The installation is projected to generate approximately 38,134 kWh annually, equating to an average of around 108 kWh per day, directly supporting building demand and EV charging requirements.
From a financial perspective, the system is forecast to achieve payback within two years, representing a strong return on investment. The project has reduced the site’s carbon footprint and strengthened energy resilience, demonstrating a practical commitment to long-term sustainability and operational efficiency.